Working like mad during the evenings this past week has had some nice results with the AC project. I am not finished by any means however, I am much much further along. I will tally up the run total again in this post as well as recap what is done :-)
The weather is getting hotter around here and you can really feel it when you are on the third floor in a knee-wall space. So here is a weekend update from the never ending project :-) Over this past weekend I was able to complete all the supply runs to the 2nd floor. I realized a few days back that I was actually going to come up about 6 feet short on supply duct. This leaves me with 25 out of the 26 required runs. Good enough for the charging of the system but probably not the best for a quiet, balanced system.
Current tally:
- 1st floor - 11 (goal 11)
- 2nd floor - 9 (goal 9)
- 3rd floor - 5 (goal 6)
- TOTAL 25 (goal 26)
I also made progress in other areas as well Thursday I pulled the wire for the condensing unit and installed the disconnect on the outside of the house. In that same day I also finished the remaining two supply runs to the 1st floor. Friday night I installed one supply into the 3rd floor and pulled the thermostat wire from the basement to the handler.
Saturday I got to work right away and installed three supply runs into the master bedroom. I also installed one more supply into the 3rd floor. During Matthews nap, I worked outside on leveling and placing the gravel and cement pad for the condensing unit. I can say I was pretty much drenched in sweat and attic yuck - all day. I was also able to finish routing the wires to the air handler and place the switch box. That left me with one final 3rd floor run to complete on Sunday. I started work Sunday at 0530 (got to beat the heat) and finished the 25th run in roughly 1.5 hours. I also had time to connect the wires into the air handler, all before coffee - (that is pretty scarry in itself).
In the afternoon on Sunday I opened the breaker box and installed two double pole breakers for the AC equipment and then closed things back up.
Things left to do:
- drain line
- complete wiring
- place condenser
- return air box?
Of course I am not finished but the Guinness is looking closer and closer. :-)