So most installers would be rapping up the project. Mean while we are just getting to the fun stuff.

http://www.footefamily.net/house/upload/2006/05/264s-thumb.jpg

Today we actually positioned the terminations into a few rooms of the house. The big accomplishment for the day was getting one supply tube all the way down to the first floor through a second floor closet. We used a very inexpensive 4 inch sewer pipe to conseal the duct in the closet getting this to fit into place was also quite fun. So this first crack at getting the AC outlets into the correct spots was successfull. I have discovered that 4-1/8 hole saw is needed for the sewer pipe to go through the cieling while smaller 3-1/2 in is ok for going into the floor. Where the AC outlet is positioned in the cieling needs to be cut using the 4 in hole saw to account for the clips to hold the face plate in position.